The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 32
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Maintain subordinate internal activity elements assigned to other work centers.
- B. Shift activities backward or forward on the time axis where more capacities are available.
- C. Increase the capacities of the work center in the project planning board.
- D. Trigger automatic capacity leveling inside the project planning board.
Answer: B,D
NEW QUESTION 33
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
- A. Basic dates of the network activity
- B. Basic dates of the WBS
- C. Forecast dates of the WBS
- D. Actual dates of the network activity
Answer: A
NEW QUESTION 34
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. The factory calendar in the work center used for the internal processing activity
- B. The unit (for example, hour, day) of the field Normal Duration field of the activity
- C. An activated Scheduling indicator in the control key of the internal processing activity
- D. The relationships between activity elements
- E. Whether the work for the internal activity is greater than its duration
Answer: A,C,D
NEW QUESTION 35
How are earliest dates and latest dates of activities scheduled?
- A. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
- B. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
- C. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
- D. Earliest dates and latest dates are scheduled by forward scheduling.
Answer: A
NEW QUESTION 36
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material master is set to external procurement.
- B. The material is assigned to the activity as a non-stock material.
- C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
- D. The availability check for material components indicates missing parts.
Answer: C,D
NEW QUESTION 37
To which object can you assign a factory calendar?
- A. Network header
- B. Material component
- C. Milestone
- D. Relationship
Answer: A
NEW QUESTION 38
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
- A. Forward
- B. Current date
- C. Only capacity requirements
- D. Backward
Answer: D
NEW QUESTION 39
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing reservations for material components
- D. Missing budget for material components
Answer: B
NEW QUESTION 40
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.
- A. If the appropriate reduction type is set in the parameters for network scheduling
- B. If the reduction strategy is set in the network header
- C. If the maximum reduction level is less than 100
- D. If the reduction strategy is set in each activity
Answer: A,B
NEW QUESTION 41
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The MRP controller for the network
- B. The person responsible for the work center
- C. The person responsible for the network activity
- D. The person responsible for the superior WBS element
Answer: A
NEW QUESTION 42
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
- A. You can shorten the project mask even when there are existing projects.
- B. You can only use numbers for a project coding mask definition.
- C. You can use the same coding mask for standard projects and operative projects.
- D. You can use an indicator to determine that only coded project numbers may be used within SAP Project System.
Answer: C,D
NEW QUESTION 43
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt of a non-stock item
- B. Goods receipt into valuated project stock
- C. Recording of external services in the service entry sheet
- D. Goods receipt into unvaluated project stock
Answer: C,D
NEW QUESTION 44
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Requirements type
- B. Requirements class
- C. Schedule line category
- D. Item category
Answer: D
NEW QUESTION 45
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The table of MRP controllers
- B. The control key
- C. The network profile
- D. The scheduling parameters for the network
Answer: D
NEW QUESTION 46
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A sold to party is necessary.
- B. A shipping point is necessary.
- C. A sales order must be created in advance.
- D. A delivery document type must be configured.
Answer: A,B
NEW QUESTION 47
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Material
- B. Resource
- C. Location
- D. Production version
Answer: B,C
NEW QUESTION 48
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
- A. Structure overview
- B. Extended capacity evaluation
- C. Individual overview capacity requirements
- D. None
- E. Capacity load work center view
Answer: C
NEW QUESTION 49
Which object is used to allocate the costs from a claim to the project structure?
- A. Network activity
- B. Internal order
- C. Claim
- D. WBS element
Answer: B
NEW QUESTION 50
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.
- A. In the project type
- B. In the project profile
- C. In the operative WBS element
- D. In the project version
- E. In the project definition of a standard WBS
Answer: B,C,E
NEW QUESTION 51
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
- A. An MRP group must be assigned.
- B. The exact lot size procedure must be used.
- C. The procurement type of the material must be internal.
- D. The materials must allow sales order or project stock.
Answer: A,D
NEW QUESTION 52
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Purchase order items
- B. Reservations
- C. Internal orders
- D. Sales order items
Answer: A,B
NEW QUESTION 53
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
- A. Planned dates
- B. Baseline dates
- C. Basic dates
- D. Forecast dates
Answer: C,D
NEW QUESTION 54
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Strict bottom-up
- B. Bottom-up
- C. Free planning
- D. Top-down
Answer: B
NEW QUESTION 55
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the project definition
- B. In the network activity
- C. In the WBS element
- D. In the material master
Answer: A
NEW QUESTION 56
......