NEW QUESTION 25
Which of the following can be maintained in a maintenance notification?
There are THREE correct answers for this Question
Response:
- A. Operations
- B. Materials list
- C. Location data
- D. Tasks
- E. Cause of damage
Answer: C,D,E
NEW QUESTION 26
Which objects can you settle?
There are TWO correct answers for this Question
Response:
- A. Maintenance order
- B. Cost center
- C. Work breakdown structure (WBS) element
- D. Profitability segment
Answer: A,B
NEW QUESTION 27
What object is always a true Controlling (CO) object?
Response:
- A. Cost center
- B. Project
- C. Internal order
- D. Profit center
Answer: D
NEW QUESTION 28
You re posting a document. In the line item, for which account must you enter a transaction type?
Response:
- A. General ledger account
- B. Material account
- C. Vendor account
- D. Asset account
Answer: A
NEW QUESTION 29
What are the benefits of using a business partner in SAP S/4HANA?
There are TWO correct answers for this Question
Response:
- A. It provides a harmonized architecture
- B. Vendors are managed separately from customers
- C. General data is unique to each role
- D. You can maintain multiple addresses for an entity
Answer: A,D
NEW QUESTION 30
What master data defines the quantity structure to create a standard cost estimate?
There are TWO correct answers for this Question
Response:
- A. Cost center
- B. Routing
- C. Bill of material
- D. Activity type
Answer: B,C
NEW QUESTION 31
Within a MRP net requirements calculation, which of the following are demand elements?
There are 3 correct answers to this question.
Response:
- A. Planned independent requirements
- B. Purchase order
- C. On hand inventory
- D. Sales order
- E. Safety stock
Answer: A,D,E
NEW QUESTION 32
Which of the following is a feature of Streamlined Procurement?
Response:
- A. Invoice processing
- B. Self-service requisitioning
- C. Supplier evaluation
- D. Source assignment
Answer: C
NEW QUESTION 33
What assigns actual costs to a project?
Response:
- A. Saving a purchase order
- B. Processing a cost forecast
- C. Posting a vendor's invoice
- D. Calculating project interest
Answer: C
NEW QUESTION 34
What are the process steps in corrective maintenance?
Response:
- A. Create Task List
Create Plan
Schedule Plan
Release Order
Complete Order - B. Create Notification
Release Order
Execute Order
Complete Order
Billing - C. Create Task List
Create Plan
Schedule Plan
Complete Order
Billing - D. Create Notification
Create Order
Release Order
Execute Order
Complete Order
Answer: D
NEW QUESTION 35
Which objects can be assigned to a purchasing organization?
There are TWO correct answers for this Question
Response:
- A. Plant
- B. Material master
- C. Vendor
- D. Controlling area
Answer: B,C
NEW QUESTION 36
What fields are required when you create a cost center?
There are TWO correct answers for this Question
Response:
- A. Person responsible
- B. Hierarchy area
- C. Address
- D. Department
Answer: A,B
NEW QUESTION 37
Which of the following areas are part of SAP SuccessFactors Employee Central?
There are THREE correct answers for this Question
Response:
- A. Employee Data
- B. Learning Management
- C. Payroll
- D. Organization management
- E. Success and Development
Answer: A,C,D
NEW QUESTION 38
Which of the following are Management Accounting organizational levels?
There are TWO correct answers for this Question
Response:
- A. Operating concern
- B. Segment
- C. Company code
- D. Controlling area
Answer: A,D
NEW QUESTION 39
Which SAP solution is used to perform marketing operations within the SAP S/4HANA suite?
Response:
- A. SAP Fieldglass
- B. SAP Ariba
- C. SAP SuccessFactors
- D. SAP Hybris
Answer: D
NEW QUESTION 40
What general ledger account information is defined at the chart of accounts level?
There are TWO correct answers for this Question
Response:
- A. Account management
- B. Account number
- C. Account balance
- D. Account group
Answer: B,C
NEW QUESTION 41
What must two company codes have in common if you want to link them to the same controlling area?
There are TWO correct answers for this Question
Response:
- A. Company code currency
- B. Fiscal year variant
- C. Operational chart of accounts
- D. Country
Answer: B,C
NEW QUESTION 42
For what network activity can you plan capacities?
Response:
- A. External activity
- B. Service activity
- C. Cost activity
- D. Internal activity
Answer: B
NEW QUESTION 43
In which situation would you create an equipment master record?
There are TWO correct answers for this Question
Response:
- A. To functionality represent the technical system structures in your company
- B. To report the usage time of an object at a functional location
- C. To report the effects of usage on the likelihood of damage to the installed equipment
- D. To report and track preventive maintenance tasks for an object
Answer: B,D
NEW QUESTION 44
How can you post internal labor costs to a network activity?
There are TWO correct answers for this Question
Response:
- A. Service entry sheet
- B. Distribution
- C. Confirmation
- D. Activity allocation
Answer: C,D
NEW QUESTION 45
You purchase raw materials with a purchase order against an internal order. During which process step are journal entries posted?
Response:
- A. Release purchase order
- B. Save purchase requisition
- C. Calculate the payment method
- D. Post valuated goods receipt
Answer: D
NEW QUESTION 46
Which of the following can be included in a customer pricing condition record?
There are TWO correct answers for this Question
Response:
- A. Surcharges
- B. Discounts
- C. Invoice amounts
- D. Order values
Answer: A,B
NEW QUESTION 47
Which of the following sequences of purchase-to-pay process steps is valid?
Response:
- A. Vendor selection
Source of supply determination
Purchase order monitoring
Goods receipt
Handling of payments - B. Determination of requirements
Purchase order handling
Handling of payments
Goods receipt
Invoice verification - C. Determination of requirements
Vendor selection
Purchase order handling
Goods receipt
Invoice verification - D. Source of supply determination
Vendor selection
Determination of requirements
Purchase order handling
Goods receipt
Answer: C
NEW QUESTION 48
What type of document is generated for an external network activity?
Response:
- A. Purchase requisition
- B. Planned order
- C. Reservation
- D. Sales order
Answer: D
NEW QUESTION 49
What can a planned order be converted to?
There are TWO correct answers for this Question
Response:
- A. A purchase requisition
- B. A production order
- C. A planned independent requirement
- D. A purchase order
Answer: A,B
NEW QUESTION 50
......
C-TS410-1809 Exam Certification Details:
| Cut Score: | 60% |
| Level: | Associate |
| Languages: | German, English, Spanish, French, Japanese, Korean, Russian, Chinese |
| Duration: | 180 mins |
| Exam: | 80 questions |
Pass SAP Certified Application Associate C-TS410-1809 Exam With 87 Questions: https://www.topexamcollection.com/C-TS410-1809-vce-collection.html