Pass SAP C-S4CPS-2108 Exam Quickly With TopExamCollection [Q12-Q32]

Share

Pass SAP C-S4CPS-2108 Exam Quickly With TopExamCollection

Prepare C-S4CPS-2108 Question Answers - C-S4CPS-2108 Exam Dumps


SAP C-S4CPS-2108 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Scope Item Level Implementation and Configuration for Core Project-Based Services, Analytics and Financials > 12%

Perform necessary tasks related to Resource Management - Project-Based Services (1KC), Customer Project Management (J11), Intercompany Processes - Project-Based Services (16T), Service and Material Procurement - Project-Based Services (J13), Sales Order Processing - Project-Based Services (J14), Internal Project Management (1A8), Time Recording - Project-Based Services (J12), Customer Project Analysis (BGI), Utilization Analysis (BGJ) and Event-Based Revenue Recognition - Project-Based Services (1IL)

Business Process Testing < 8%

Describe the concepts of Business Process Testing and prepare and execute a Business Process Test Plan.

SAP Activate Methodology and Best Practices 8% - 12%

Describe the SAP Activate Implementation Methodology, best practices and Content Lifecycle Management for RISE with SAP S/4HANA Cloud (public).

Integration and Extensibility < 8%

Describe the concepts of extensibility and integration and their implementations.

Configuration and Reporting 8% - 12%

Identify the implementation phases and scope and perform key Guided Configuration; describe Expert Configuration; explain SAP Cloud Platform Identity Authentication Service; perform core user management in SAP S/4HANA Cloud; and identify Key Solution configuration settings for integration.

Data Migration < 8%

Identify Self-Service Configuration UIs for data migration, prepare data migration, perform data migration, and describe best practices for managing data migration between release lifecycles.

SAP S/4HANA Cloud (public) - Professional Services Overview 8% - 12%

Describe the RISE with SAP strategy and solution scope of SAP S/4HANA Cloud (public) in general and the details for the Professional Services solution and innovations.



C-S4CPS-2108 Exam Certification Details:

Exam:80 questions
Sample Questions: SAP C-S4CPS-2108 Exam Sample Question
Level:Associate
Duration:180 mins
Cut Score:60%
Languages:English

 

NEW QUESTION 12
What are your options if an out-of-the-box integration between SAP S/4HANA Cloud and another SAP solution is NOT available? Note: There are 2 correct Answers to this question.

  • A. Unrestricted firewall
  • B. Integration tools
  • C. Whitelisted APIs
  • D. Infrastructure as a Service

Answer: B,C

 

NEW QUESTION 13
Which apps can be accessed from the KPI cards in the advanced version of Fiori app Resource Management for Projects? Note: There are 2 correct Answers to this question.

  • A. Manage Project Staffing
  • B. Manage Resource Utilization
  • C. Manage Resource Requests
  • D. Manage Project Assignments

Answer: A,B

 

NEW QUESTION 14
Which components are required to integrate SAP S/4HANA Cloud with SAP Project Companion? Note:
There are 3 correct Answers to this question.

  • A. SAP CoPilot
  • B. SAP Cloud Platform Mobile Services subscription
  • C. SAP Cloud Platform Identity Authentication
  • D. SAP Concur
  • E. SAP Cloud Platform consumer account

Answer: B,C,E

 

NEW QUESTION 15
What SAP solution provides collaboration capabilities to increase workforce productivity?

  • A. SAP SuccessFactors Employee Central
  • B. SAP Concur
  • C. SAP Jam
  • D. SAP Fieldglass

Answer: A

 

NEW QUESTION 16
In what scenario will there be multiple resource requests for the same project role?

  • A. Multiple skills have been assigned to the same project role.
  • B. Multiple work items have been created for the same project role.
  • C. The resource assigned to the work package consists of multiple individual employees.
  • D. The estimated effort for the project role exceeds the work package duration.

Answer: B

 

NEW QUESTION 17
Which types of datasets are required for predictive scenarios? Note: There are 2 correct Answers to this question.

  • A. Testing Dataset
  • B. Training Dataset
  • C. Active Dataset
  • D. Apply Dataset

Answer: B,C

 

NEW QUESTION 18
What are the available methods through which you can fill staging tables in the SAP HANA database of the target system? Note: There are 3 correct Answers to this question.

  • A. Customer's ETL tools
  • B. SAP SQL Anywhere
  • C. XML templates
  • D. SAP HANA Smart Data Integration (SDI)
  • E. SAP Smart Data Access

Answer: A,C,D

 

NEW QUESTION 19
You are reviewing the Open Resource Requests KPI card in the Fiori app Resource Management for Projects. What are the possible urgency groupings? Note: There are 2 correct Answers to this question.

  • A. Very High
  • B. Critical
  • C. Upcoming
  • D. Overdue

Answer: A,D

 

NEW QUESTION 20
In what phase of the SAP Activate methodology do you test the business processes?

  • A. Prepare
  • B. Deploy
  • C. Explore
  • D. Realize

Answer: D

 

NEW QUESTION 21
In case temporary adjustments have been entered, which of the following tasks can be performed to adjust the recognized revenue? Note: There are 2 correct Answers to this question.

  • A. Execute a periodic revenue recognition run
  • B. Recalculate revenue recognition for the affected WBS elements
  • C. Recalculate planned values at work package level
  • D. Adjust PoC manually

Answer: A,B

 

NEW QUESTION 22
What tasks can the Resource Manager perform through the Fiori apps that are available in the advanced version of Resource Management? Note: There are 2 correct Answers to this question.

  • A. Monitor and analyze resource utilization
  • B. Maintain skills for work items
  • C. Staff resource requests for project roles
  • D. Transfer actual working times

Answer: A,C

 

NEW QUESTION 23
How does the system determine the default currency for an internal project?

  • A. From the settings of the Create Internal Project app
  • B. From the company code of the service organization
  • C. From the controlling area of the profit center
  • D. From the user default settings

Answer: B

 

NEW QUESTION 24
Which of the following are capabilities of the Fiori apps used in the SAP Best Practices Service and Material Procurement - Project-Based Services (J13) scenario? Note: There are 3 correct Answers to this question.

  • A. Create purchase requisitions
  • B. Create timesheet entries
  • C. Create reservations
  • D. Create supplier invoices
  • E. Create purchase orders

Answer: B,D,E

 

NEW QUESTION 25
Which of the following are benefits of the SAP Best Practices Event-Based Revenue Recognition - Project-Based Services (1IL) scenario? Note: There are 3 correct Answers to this question.

  • A. Full transparency
  • B. Real-time reporting
  • C. Reconciliation
  • D. Margin calculation

Answer: A,B,C

 

NEW QUESTION 26
Which of the following Business Add-Ins (BAdIs) are available for the Fiori app Create Internal Projects?
Note: There are 3 correct Answers to this question.

  • A. Authorization to Change Project Stage
  • B. Generate Project IDs
  • C. Project Validation
  • D. Project Element Determination
  • E. Send email

Answer: A,B,E

 

NEW QUESTION 27
In the SAP Best Practices Intercompany Processes - Project-Based Services (16T) scenario, how is the intercompany sales order created?

  • A. Manually as a one time activity for each distinct project customer
  • B. Manually for each project engagement
  • C. Manually as a one time activity in your SAP S/4HANA Cloud tenant
  • D. Manually as a one time activity for each delivering company

Answer: D

 

NEW QUESTION 28
Which activity do you perform during the data load preparation?

  • A. Simulate data load in the new cloud system
  • B. Resolve data issues from the simulation process
  • C. Define specifications for data extraction on legacy system
  • D. Fill in migration templates with legacy data

Answer: D

 

NEW QUESTION 29
In the Fiori app Manage My Timesheet, which actions are possible in the My Tasks side panel? Note:
There are 2 correct Answers to this question.

  • A. View the total number of hours recorded per task
  • B. Create, edit, and delete task entries for the selected week
  • C. View the approved and rejected time entries
  • D. Sort by recently used tasks

Answer: A,B

 

NEW QUESTION 30
What is the purpose of the Starter system in the SAP S/4HANA Cloud implementation project?

  • A. To demonstrate the customer's personalized solution, including process flows, the organizational structure, and authorizations
  • B. To demonstrate SAP Best Practices processes in a preconfigured system and identify customer personalization requirements
  • C. To configure the customer's personalized solution for demonstration and testing during the Realize phase
  • D. To conduct a blueprint workshop to identify all customer requirements for a completely customized solution

Answer: B

 

NEW QUESTION 31
Which processes are supported by the SAP Best Practice Sales Order Processing - Project-Based Services (J14) scenario? Note: There are 2 correct Answers to this question.

  • A. Billing processing
  • B. Intercompany processes
  • C. Sales order management
  • D. Sales contract management

Answer: A,B

 