NEW QUESTION 102
Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?
- A. Timescale
- B. Costs
- C. Scope
- D. Risk
Answer: C
NEW QUESTION 103
Which is a valid statement about the Project Support role?
- A. Produces Checkpoint Reports for the Project Manager
- B. Can be performed by the Project Manager
- C. Can be combined with the Project Assurance role
- D. Is an optional role for a PRINCE2 project
Answer: B
NEW QUESTION 104
What is a goal of the 'implement' step within the recommended risk management procedure?
- A. To monitor the effectiveness of actioned risk responses
- B. To prepare specific management responses to identified risks
- C. To communicate information related to the risks faced by the project
- D. To estimate the risk to the project in terms of probability and impact
Answer: D
NEW QUESTION 105
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
- A. BusinessCase
- B. Quality
- C. Plans
- D. Risk
Answer: A
NEW QUESTION 106
Which role is responsible for appointing the senior user in a project that is independent from a program?
- A. Corporate, program management or the customer
- B. Project assurance
- C. The project manager
- D. The executive
Answer: A
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-roles-and-responsibilities/
NEW QUESTION 107
What process provides the information required to decide whether to authorize the delivery of a project?
- A. Directing a Project
- B. Starting up a Project
- C. Managing Product Delivery
- D. Initiating a Project
Answer: D
NEW QUESTION 108
Where should decisions regarding the tailoring of the project be recorded?
- A. Project initiation documentation
- B. Project mandate
- C. Stage plan
- D. Project brief
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
NEW QUESTION 109
Which are advantages of a clear end to a project?
1. No further costs will be incurred by the project
2. Project products will be transferred to operations and support
3. All benefits will have been achieved
4. The project brief will be re-baselined
- A. 1 and 4
- B. 2 and 3
- C. 1 and 2
- D. 3 and 4
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Closing_a_Project
NEW QUESTION 110
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Directing a project
- B. Starting up a project
- C. Controlling a stage
- D. Managing a stage boundary
Answer: C
Explanation:
Explanation
Reference
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage-process-in-p
NEW QUESTION 111
Which is a true statement about PRINCE2 event-driven controls.
- A. Event-driven controls are used for decision making
- B. Checkpoint Reports are event-driven controls
- C. Event-driven controls are produced at the frequency defined in a Work Package
- D. Event-driven controls take place at predefined periodicintervals
Answer: A
NEW QUESTION 112
Identify the missing word in the following sentence.
A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.
- A. dis-benefits
- B. risks
- C. benefits
- D. issues
Answer: C
Explanation:
Section: Volume B
Explanation
A Benefit is the measurable improvement resulting from an outcome that is perceived as an advantage by one or more stakeholders.
Reference http://p2.tech-academy.co.uk
NEW QUESTION 113
Who does the Team Manager report to and take direction from?
- A. Project Assurance
- B. Project Support
- C. Project Board
- D. Project Manager
Answer: D
NEW QUESTION 114
Which is NOT one of the PRINCE2 integrated elements?
- A. The products
- B. The processes
- C. The themes
- D. Tailoring PRINCE2 to the project environment
Answer: A
NEW QUESTION 115
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project
Assurance provides the same assurance to all the project's stakeholders.
- A. Project Manager
- B. Executive
- C. corporate or programme management organization
- D. Suppliergroups
Answer: C
NEW QUESTION 116
What takes place during the Closing a Project process?
- A. Ownership of the project's products is transferred to the customer
- B. The project closure notification is reviewed and approved
- C. An End Stage Report is prepared for the final stage
- D. The post-project benefits reviews are performed
Answer: A
NEW QUESTION 117
......
PRINCE2-Foundation certification guide Q&A from Training Expert TopExamCollection: https://www.topexamcollection.com/PRINCE2-Foundation-vce-collection.html