PRINCE2 Foundation Sample Questions:
1. Which of the following Plans are approved by the Project Manager?
A) Project Plan
B) Exception Plan
C) Team Plan
D) Stage Plan
2. Which of the following is a specific quality review team role?
A) User
B) Project Support
C) Approver
D) Reviewer
3. In which situation might the Controlling a Stage process be used?
A) Managing support activities following the handover of the products to the operational environment
B) Managing the activities of a complex programme
C) Managing a long initiation stage of a complex project
D) Creating an Exception Plan to replace the current Stage Plan
4. According to PRINCE2, which of the following is a characteristic of a project compared to that of business operations?
A) Creates products
B) Delivers benefits
C) Incurs cost
D) Introduces business change
5. According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?
A) The supplier is unlikely to comprehend the detailed schedule
B) Sufficient detail is only known once the relevant stage has begun
C) It can be difficult to predict the actual performance of resources
D) All aspects of planning become more difficult the further into the future they extend
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: D | Question # 5 Answer: D |