SAP C_TS422_2601 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing |
| Exam Number: | C_TS422_2601 |
| Related Certifications: | SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing |
| Exam Duration: | 180 minutes |
| Passing Score: | 64% |
| Available Languages: | German, English, Spanish, Japanese, French, Chinese |
| Exam Price: | $541 USD |
| Certificate Validity Period: | 12 months |
| Exam Format: | Performance-based tasks, Multiple choice, Multiple response, Scenario-based |
| Real Exam Qty: | 80 - 100 |
| Recommended Training: | TS422 - SAP S/4HANA Production Planning and Manufacturing II TS421 - SAP S/4HANA Production Planning and Manufacturing I |
| Exam Registration: | SAP Certification Shop |
| Sample Questions: | SAP C_TS422_2601 Sample Questions |
| Exam Way: | Online proctored or Onsite at SAP authorized test centers; open-book allowed |
| Pre Condition: | Basic knowledge of SAP S/4HANA navigation and manufacturing processes; recommended completion of courses TS421 and TS422 |
| Official Syllabus URL: | https://training.sap.com/certification/c_ts422_2601-sap-certified-associate---sap-s-4hana-cloud-private-edition-production-planning-and-manufacturing/ |
SAP C_TS422_2601 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Production Orders | 12% - 18% | - Order Creation and Structure - Order Settlement and Closing - Order Release and Execution - Availability Check and Capacity Check |
| Lean Manufacturing and Kanban | 8% - 12% | - Repetitive Manufacturing - Kanban Process and Setup |
| Advanced Planning (PP/DS) | 8% - 12% | - Heuristics and Planning Functions - Pegging and Alerts |
| Capacity Planning | 8% - 12% | - Finite Scheduling Concepts - Capacity Leveling and Scheduling - Capacity Evaluation |
| Integration and Analytics | 10% - 15% | - Integration with Finance / Controlling - Manufacturing Reporting and Analytics |
| Process Orders | < 8% | - Master Data for Process Manufacturing - Process Order Management |
| Master Data in SAP S/4HANA | 12% - 18% | - Production Versions - Bill of Materials (BOM) - Work Centers and Routings - Material Master Data |
| Demand Management | < 8% | - Demand Strategies - Planned Independent Requirements |
| Material Requirements Planning (MRP) | 8% - 12% | - Procurement Proposals - MRP Logic and Planning Run - MRP Types and Parameters |
SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Sample Questions:
What can you use stard heuristics in Advanced Planning (PP/DS) for?
- A. To automate material movements in material staging
- B. To solve planning problems for defined objects
- C. To set default values in production master data
- D. To optimize costs times in production plans
Correct Answer: B 🗳️
How can you set up the supply source for the Kanban process in SAP S/4HANA Cloud Private Edition?
Note: There are 3 correct answers to this question.
- A. Use purchase orders for external procurement.
- B. Use run schedule quantities for inhouse production.
- C. Use quotations for internal external procurement.
- D. Use stock transfer reservations for stock transfer.
- E. Use purchasing costs for automated source prioritization.
Correct Answer: A,B,D 🗳️
What does a line hierarchy in repetitive manufacturing represent?
- A. A production line with prioritized alternative work centers
- B. A production line with more than one work center
- C. A production line with a parallel sequence in the routing
- D. A production line with an alternative sequence in the routing
Correct Answer: B 🗳️
Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks?
Note: There are 2 correct answers to this question.
- A. Resource network
- B. Resource hierarchy
- C. Resource selection
- D. Resource matrix
Correct Answer: A,C 🗳️
What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
- A. A sales order is delivered.
- B. MRP creates a dependent requirement.
- C. A sales order is created.
- D. MRP creates a planned order.
Correct Answer: C 🗳️