CompTIA Project+ Sample Questions:
1. A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
A) Review the task start and finish dates.
B) Assess the risk register's new items.
C) Analyze the assigned hours.
D) Obtain additional resources.
2. A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
A) Project manager
B) Sponsor
C) Project management office
D) Project team
3. The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources.
Which of the following should the project manager do to obtain the resources?
A) The project manager should ask the project team members to take on more tasks to complete the project on time.
B) The project manager should terminate the project until additional resources are added to the project.
C) The project manager should hire additional resources temporarily to complete the project.
D) The project manager should identify and document the reasons for the additional resources in a change request.
4. During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
A) 12 days
B) 14 days
C) 16 days
D) 19 days
5. Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
A) Smoothing
B) Accepting
C) Withdrawing
D) Compromising
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: B | Question # 3 Answer: D | Question # 4 Answer: A | Question # 5 Answer: C |

We're so confident of our products that we provide no hassle product exchange.


By Enoch